Back to Recent Projects

Case File: No.PW03
Contract Title: Eltham Palace
Commenced: Oct 98
Completed: Feb 99
Works Carried Out: Moat Dredging
eltham01

Constructing temporary dam to half the moat. Half of the moat was drained down and the fish were temporarily displaced to the half not drained.

eltham02

Grass protection was laid where the plant machinery were to be used on the bank for silt removal.

Lagoons were constructed to contain the dredged silt whilst drying out. 6" pumps and pipework were used to transport the silt minimising the effect to the existing surroundings.

eltham03
eltham04 The surrounding grounds were kept in good order at all times.

A 3 ton mini-digger was used to handle the material where it was too large to be pumped

eltham05